EC Report
1. Project Details
   i. Proposal No. : SIA/MP/MIN/94452/2019    ii. File No. : 6140/2019    iii.Short narrative of the project: Bilokalan Ochre Deposit Mine    iv. Project Sector : Non-Coal Mining    v. Subcategory : B2    vi. Company/Proponent : SUDAMA BANSAL BILOKALAN
  vii.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.Madhya PradeshShivpuriShivpuri
 
viii. Uploaded EC Compliance report by regional office of MoEFCC: NIL    viii.Date of TOR Granted N/A
  Important Dates
Important Dates
Accepted by SEIAA and forwarded to SEAC Accepted by SEAC EC Granted
23 Apr 201925 Apr 201924 Jun 2019
2. Uploaded Documents of EIA/EMP, Risk Assessment, GPS, Toposheet, Form - 1, Pre Feasibility Report, Form - 1(A)
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment    iii.Shape of the project land: Block (Polygon) iv.GPS file: Annexure-GPS File v.Toposheet file: Annexure-Toposheet file vi. Form - 1: Annexure- Form - 1 vii.Pre Feasibility Report / Conceptual Plan : Annexure-Pre Feasibility Report/Conceptual Plan viii.Mining Plan: Annexure-Mining Plan   ix. Uploaded Cover Letter: Annexure-Cover Letter   x. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   xi. Remarks: LOI, MP Approval letter, 500 meter, Tehsildar, DFO, Panchsala, Khasra Map, DSR and Distance Map of Madhav National Park.
3. Additional Detail Sought:   NIL
4. Accredited Consultant Details
   i. Accreditation status : No    ii. Reason for not hiring the Consultant : It is B2 Category project. RQP is submitting this project.
Essential Details Sought
Essential Details Sought
S.no. EDS Sought Date EDS Sought Letter
1.07/02/2019Please submit District Survey Report and detail of Eco-sensitive Zone.2.01/01/1900The corrections have been made as per the instruction received.3.02/03/2019Please submit Tehsildar Letter,500m Letter and upload complete Approved Mining Plan and detail of Eco-sensitive Zone.4.01/01/1900The corrections have been made as per the instruction received.5.08/03/2019Detail of Eco-sensitive Zone, lease sanction Letter and Khasra Panchshala.6.01/01/1900The corrections have been made as per the instruction received.7.12/03/2019Provide the distance of Mining site in eco sensitive zone8.01/01/1900The corrections have been made as per the instruction received.9.13/03/2019submit the letter of DFO clarify the mine site is not present in eco sensitive zone.10.01/01/1900The corrections have been made as per the instruction received.11.08/04/2019Please submit Tehsildar Letter,District survey report and Mining officer Letter of 500 m information.12.01/01/1900The corrections have been made as per the instruction received.13.08/04/2019Please submit 500 m Letter and Tehsi;dar Letter14.01/01/1900The corrections have been made as per the instruction received.15.08/04/2019Please submit complete document16.01/01/1900The corrections have been made as per the instruction received.17.08/04/2019Please submit complete document18.01/01/1900The corrections have been made as per the instruction received.19.08/04/2019Please submit complete document20.01/01/1900The corrections have been made as per the instruction received.21.08/04/2019Please submit complete document22.01/01/1900The corrections have been made as per the instruction received.23.09/04/2019Please submit complete document24.01/01/1900The corrections have been made as per the instruction received.
 
5. Undertaking
The aforesaid application and documents furnished here with are true to my knowledge
   i. Name : SUDAMA BANSAL BILOKALAN    ii. Designation : Lessee    iii. Company : SUDAMA BANSAL BILOKALAN    iv. Address : Village-Bilokalan, Tehsil-Shivpuri, District-Shivpuri, M.P
5. Recommendation by SEAC/SEIAA
Recommendation
Recommendation By Date of Recommendation Recommendation Letter Remarks
SEAC 16 May 2019 N/AEC Recommended.
SEIAA 15 Jul 2019 N/AEC Granted