Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Details of Project:
(a)Name of the project(s) Capacity expansion in existing Cement Grinding Unit (from 2 MTPA to 2.5 MTPA = 25%)
(b)Name of the Company / Organisation DIAMOND CEMENTS GRINDING UNIT IMLAI
(c)Registered Address Diamond cements- Grinding unit Imlai (prop: Heidelbergcementindia Limited) Village & Post- Imlai Damoh (M.P.),Damoh,Madhya Pradesh-470661
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Umesh Kumar Verma
(b)Designation (Owner/ Partner/ CEO) vicepresident
(c)Address Diamond cements- Grinding unit Imlai (prop: Heidelbergcementindia Limited) Village & Post- Imlai Damoh (M.P.),Damoh,Madhya Pradesh-470661
(d)Pin code 470661
(e)E-mail umeshkumar.verma@heidelbergcement.in
(f)Telephone No. 248903
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity3(b) Cement plants
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/MP/IND/105704/2019
(e)Master Proposal Number(Single Window) SW/105702/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 1
(g)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 270/2
(b)Pincode 470661
(c)Bounded Latitudes (North) FROM 23.864916667 To 23.86575
(d)Bounded Longitudes (East) FROM 79.4272 To 79.4438889
(e)Survey of India Topo Sheet No. 55m9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 360
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 8
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Madhya Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Madhya PradeshDamohDamohImlai
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By CPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on NIL
(iii)Letter No. AW46487
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Cement20000005000002500000Tons per Annum(TPA)Road,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)grinding unit20000005000002500000
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 29 Dec 2016
(iv)Valid Upto 31 Jan 2020
(v)File No. 146143
(vi)Application No. 44549
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 7.50
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.50
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.17
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.20
(e) Funds Allocated for Environment Management Capital(%) 0.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 210000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 210000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Flyash dry875000Tons per Annumopen marketRoad,Rail100 Open MarketCopy of Linkage
(2.)Clinker1540000Tons per AnnumcaptiveRoad,Rail20 CaptiveCopy of Linkage
(3.)Gypsum85000Tons per Annumlocal marketRoad,Rail300 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 25 To 30
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 22
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater2500Copy of Permission LetterPipelineOpen WellCGWA/NOC/IND/ORIG/2018/397029 Aug 2018100
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic use8090STPReuse within the Plant & Recycling,Green Belt Renewal Plant80
16.1.
(a)Total Waste Water Generation 80
(b)Total Discharged Water 0
(c)Total Reused Water 80
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Metal ScrapIndustrial Waste150Tons200RoadAuthorized Recyclers
(2.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)10Kilolitre200RoadAuthorized Recyclers
(3.)Lead Acid batteriesHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.6Tons200RoadAuthorized Recyclers
(4.)Used Grease 5.2 categoryHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5Tons200RoadAuthorized Recyclers
(5.)STP SludgeOthersSTP sludge2Tons0OthersNAOthersgardning
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube30.252.80.1730.5260
(2.)SO2Microgram per Meter Cube42.80.254.2580
(3.)PM10Microgram per Meter Cube68.92.81.770.6100
(4.)NOxMicrogram per Meter Cube12.362.80.6312.9680
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Cement mill-1NA371.2PM100.76
(2.)Cement MIll-2NA37.51.5PM100.76
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 13600
(b)Source MPSEB
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 75
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 75
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 19482
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 1727
(d)Surface Water Bodies 0
(e)Settlements 3472.25
(f)Industrial 75
(g)Forest 828.00
(h)Mangroves 0
(i)Marine Area 0
(j)Others : NA 0
    Total 25584.25
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant5.80
(2.)Township7.64
(3.)Green belt33.21
(4.)OthersRailway Siding23.45Railway Siding
(5.)Water Reservoir4.90water body, Road
Total 75
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA100NONE WITH IN 10KM RADIUS
(2.)WLSNA100NONE WITH IN 10KM RADIUS
(3.)NPANA100NONE WITH IN 10KM RADIUS
(4.)ESAsNA100NONE WITH IN 10KM RADIUS
(5.)ESZsNA100NONE WITH IN 10KM RADIUS
(6.)CorridorsNA100NONE WITH IN 10KM RADIUS
(7.)Wildlife CorridorsNA100NONE WITH IN 10KM RADIUS
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestDamoh RF3.6SSE
(2.)Archaeological SitesNA100None within 10km radius
(3.)Defence InstallationsNA100None within 10km radius
(4.)OthersNANA100None within 10km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 75
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired already aquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kopra River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 4.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 115
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 214
(e)No. of working days 365
(f)Total Manpower 329
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt33.21033
(2.)No. of Plants1090630109063
(3.)Percentage of Total Project Area44.28044
(4.)Funds Allocated20020
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialProposed Programme under CSR 1. Infrastructure Creation: a. Drinking Water Infrastructure: b. Irrigation Infrastructure: • Enhancement and safe guarding of surface water bodies • Soil and water
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABE/EIA/1619/RA0071
(ii)Name of the EIA Consultant Creative Enviro Services
(iii)Address SR-4, Shriram Kunj, E-8, Bharat Nagar, Bhopal
(iv)Mobile No. 9425009319
(v)Landline No. 0755429931
(vi)Email Id creative.bpl@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 23 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan
(b)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(c)Uploaded Cover Letter Copy of Cover Letter
(d)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(f)Uploaded Updated Form1 Copy of Updated Form1
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)20/05/2019Kindly re- submit the updated form I it is showing some error to open.
(2.)11/06/2019The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantUmesh Kumar Verma
Designationvicepresident
Name of Company (Applicant Name should not be given here)DIAMOND CEMENTS GRINDING UNIT IMLAI
AddressDiamond cements- Grinding unit Imlai (prop: Heidelbergcementindia Limited) Village & Post- Imlai Damoh (M.P.)