Form-1
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
1. Basic Informations
2.
Address for the correspondence:
(a)Name of the Applicant Anurag Maheshwari
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Khasra No 374,375/1, 375/2 part, 376/1 part, 376/2, 377/1, 377/2 part, 378/2, 378/3, 378/4, 379/1, 379/2, 379/3, 379/4, 379/5, 379/6, 379/7, 380/1/2/5, 385/P, 375/P, 385/2, 386/1, 389/1, 389/2, 390/1, 390/2, 386/2, 389/1, 390/2 AT village Bijalpur Te,Indore,Madhya Pradesh-452012
(d)Pin code 452012
(e)E-mail avasashristi5@gmail.com
(f)Telephone No. 23816262
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(a) Building and Construction projects
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/MP/MIS/153286/2020
(e)Master Proposal Number(Single Window) SW/153285/2020
(f)EAC concerned (for category A Projects only) Infrastructure and Miscellaneous Projects  +  CRZ
(g)Project Type(New/Expansion/Modernization) Fresh EC
4.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Madhya Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Madhya PradeshIndoreIndoreBijalpur
5.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(c)Reason -1
(d)Supporting Document Copy of Supporting Document
Project Profile
Location of the project INDORE
Town / Village
(Name of more than one town may be entered by separating with)
Bijalpur Plot/Survey/Khasra No.
(Name of more than one town may be entered by separating with)
Khasra No 374,375/1,375/2part,376/1 part ,376/2 , 377/1 , 377/2part, 378/2,378/3, 378/4, 379/1, 379/2, 379/3, 379/4, 379/5,379/6, 379/7,380/1/2/5,
State Madhya Pradesh District Indore
Tehshil Indore Pincode 452003
Nearest railway station Indore Railway Station Distance from the project site 6
Nearest airport Indore Airport Distance from the project site 7
Nearest Town/City/District Headquarters INDORE Distance from the project site 2
Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) INDORE MUNICIPAL CORPORATION Upload GPS file Uploaded GPS file
Shape of the project land Block (Polygon) Site alternative under consideration(If any) Uploaded Site alternative under consideration
Brief summary of project Uploaded Brief summary of project
Does your project location falls under out of any following areas Indore (M.P.)
Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) 40859.04 Existing Built Up Area(In Meter /Sqr) 40859.04
Does it attract any of the general conditions given below? No
Does it attract the specific condition given below? No
Interlinked Projects No
Whether separate application of interlinked projects has been submitted? Date of Submission
Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? Yes
Status In-Principle(Stage-I) Approval Obtained
MoEFCC file number FC/MP/OTHERS/5042/2020 Date of In-Principle 11/05/2020
Area diverted 00 Upload Clearance Letter Uploaded Clearance Letter
Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? No
Whether the proposal involves approval/clearance under the C.R.Z notification,2011? No
Whether there is any Government Order/Policy relevent/relating to the site? No
Forest land involved(hectares) 00
Is there any litigation pending against the project? No


Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes Permanent change in land use will occur due to Construction of Residential villas. Project site is a plain land with small bushes and grass.
1.2 Clearance of existing land, vegetation and buildings? Yes Project site consists of grass, bushes and shrubs. Proponent has constructed buildings within the project site.
1.3 Creation of new land uses? Yes The proposed site will be used for construction of Residential villas.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Soil testing was done.
1.5 Construction works? Yes Construction of Residential villas.
1.6 Demolition works? No No Demolition works were envisaged as there were no old structures in the proposed site.
1.7 Temporary sites used for construction works or housing of construction workers? No Most of the workers will be hired from the nearby areas. Temporary sheds was provided for security persons and outside
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations No The proposed construction involves development of Residential villas which requires adequate engineered earthworks. Excavation has been done for construction of footing & foundations. The excavated soil of about 28,456 cum has been used within the site for leveling & for internal roads.
1.9 Underground works including mining or tunneling? No Not Applicable
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing processes? No Not Applicable
1.14 Facilities for storage of goods or materials? Yes Temporary site office/Room/Shed at site.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Treated in Sewage treatment plant. • Salt glazed vitrified pipes or HDPE pipes for sewage collection. • It has been seen that there is no leakage or mixing of sewage with drinking or ground water sources. • Treated effluents will be disposed in Rain water harvesting pits/Storm water Drains.
1.16 Facilities for long term housing of operational workers? Yes Temporary site office/Room/Shed at site.
1.17 New road, rail or sea traffic during construction or operation? No Not Applicable
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Not Applicable
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not Applicable
1.20 New or diverted transmission lines or pipelines? No Not Applicable
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No Not Applicable
1.22 Stream crossings? No Not Applicable
1.23 Abstraction or transfers of water from ground or surface waters? No Not Applicable
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No Due to proposed project there were not any changes in water bodies, drainage pattern etc. Runoff will be managed by adequate storm water drain systems.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transfer of material done by vehicles to the construction site.
1.26 Long-term dismantling or decommissioning or restoration works? No None envisaged
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No None envisaged
1.28 Influx of people to an area in either temporarily or permanently? Yes During operation the Residential Apartments occupied by different companies by temporarily.
1.29 Introduction of alien species? No None envisaged
1.30 Loss of native species or genetic diversity? No None envisaged
1.31 Any other actions? No None envisaged
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes land – 20550.00 m2
2.2 Water (expected source & competing users) unit: KLD Yes Total water requirement for the project is 214 KLD. Source of the water is municipal water supply. Water requirement details are enclosed as Annexure-2.
2.3 Minerals (MT) No Not Applicable
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Coarse & Fine Aggregate, Granite, Kota stone, marble bricks, sand, cement, steel. From local traders or nearby sites.
2.5 Forests and timber (source – MT) Yes Timber for Doors & windows
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes About 1544 KW power will be required for the Project and it will be sourced from Madhya Pradesh pashchim Kshetra Vidyut Vitran company Ltd. Backup power supply is planned for the project through DG Set (to be placed in acoustic chamber). Capacity – 30 KVA (15 KVA x 2)
2.7 Any other natural resources (use appropriate standard units) No Not Applicable
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No No hazardous substances (as per MSIHC rules) are used in the proposed project. Therefore no hazardous waste is generated.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No None envisaged
3.3 Affect the welfare of people e.g. by changing living conditions? No Socio Economic conditions will be improved as the building will employ people.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not Applicable
3.5 Any other causes No Not Applicable
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not Applicable
4.2 Municipal waste (domestic and or commercial wastes) Yes The total municipal waste generated from the proposed project is 794 kg/day. Details enclosed as Annexure - 3.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No Not Applicable
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge from effluent treatment Yes Sludge from STP sent to greenbelt development.
4.7 Construction or demolition wastes Yes Bio-degradable/ Non bio-degradable waste will be sent to municipal solid waste management facility. • Recyclable waste is sold to local vendors.
4.8 Redundant machinery or equipment No Most of the equipment used for the construction will be hired and any surplus equipment and material that is found will be sold off to the appropriate agencies.
4.9 Contaminated soils or other materials No No soil Contamination is anticipated as the proposed project being a construction project all the waste generated recyclable in nature (Domestic in nature).
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes Yes Solid Waste like rubbles, used up cement, broken bricks etc which used for filling up of low lying areas during development stage.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Emissions will be mainly from vehicles running at the project site during construction and operation period and secondly from the DG set used for backup power source (during power failures only for a short duration). High Speed Diesel (HSD) will be used for the DG sets. The main emissions will be SO2 and NOx .
5.2 Emissions from production processes Yes Not Applicable as this is a construction project
5.3 Emissions from materials handling including storage or transport Yes The main emissions during the construction were PM (Particulate Matter) from loading and unloading of material on the site. SO2 and NOx from the combustion of fossil fuels and from the vehicles. The particulate matter controlled by sprinkling water at regular intervals on paved roads. The SO2 and NOx will be controlled by proper maintenance of the vehicles.
5.4 Emissions from construction activities including plant and equipment Yes Fugitive emissions are likely during the construction activities due to use of construction equipment. These are temporary in nature. The main emissions during the construction will be PM from the loading and unloading of materials on the site. SO2 and NOx from the combustion of fuels in construction equipment used which would be controlled.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Fugitive emissions are likely during the construction activities due to use of construction equipment. These are temporary in nature. The main emissions during the construction will be PM from the loading and unloading of materials on the site. SO2 and NOx from the combustion of fuels in construction equipment used which would be controlled.
5.6 Emissions from incineration of waste No Not Applicable
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not Applicable
5.8 Emissions from any other sources No Not Applicable
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise level of 75 dB (A) is anticipated during activities such as drilling, concrete mixing and crushing etc. These are temporary in nature and minimized by adopting proper maintenance such as greasing oiling and insulations (enclosures) for noise abatement.
6.2 From industrial or similar processes No Not Applicable as this was a construction project.
6.3 From construction or demolition Yes Construction activities such as Site preparation, Laying of roads, Drilling, Crushing.
6.4 From blasting or piling Yes Not Applicable as no blasting involved
6.5 From construction or operational traffic Yes Vehicles or Trucks shifting the load from one place to another
6.6 From lighting or cooling systems Yes HVAC will be used for this Residential Apartments
6.7 From any other sources Yes From DG set noise is anticipated but this will be for a very short period of time during power failures.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No No hazardous substances are used in the proposed project as this is a construction project
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No The domestic waste will be passed through the closed conduits/ drains/ sewer lines to the STP for the treatment, part of the treated water is reused for flushing and green belt
7.3 By deposition of pollutants emitted to air into the land or into water No In Building and construction project the air pollutants are minimal; to minimize the same greenbelt will be developed along the boundary and roads.
7.4 From any other sources No None envisaged
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Proper Environmental Management Plan will be followed for air, water, noise pollution and solid waste management. Hence no long term impacts are envisaged and this being a construction project the impact felt on the area will be temporary in nature as most of the impacts are all construction impacts.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No This being construction project no explosion, spillage, fire etc from storage, handling, use or production of hazardous substances will be take place. Fire Fighting systems will be installed and safety precautions will be followed as per the
8.2 From any other causes No Not Applicable
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No None envisaged. The project site falls in the seismic zone-II, which is seismically least active zone.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Yes both construction and operation phase will enhance the supporting, utilities, ancillary development in the area around. Improved aesthetic look by avenue plantation
9.2 Lead to after-use of the site, which could have an impact on the environment Yes A positive impact on the environment in the area is anticipated due to the development of green belt.
9.3 Set a precedent for later developments Yes The proposed development will facilitate further sustainable development of Residential Apartments areas.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No None envisaged as the proposed development is a construction project.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Ralamandal Wild Life Sanctuary -8.0 km Deoguradia Protected Forest-9.0 km
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Bilawali Talab-6 km(NE) Sukniwas lake - 5km(N) Sirpur Tank-10 km (N) Khan River-7km (N) Protected Monuments as per ASI Krishnapura Chhatries, LalbaughPalace, Khajrana Temple, RajwadaAnnapurna Temple, Geeta BhavanKanch Mandir & Bada Ganpati lied Within 15 km from proposed site.
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration Yes Ralamandal Wild Life Sanctuary -8.0 km Deoguradia Protected Forest-9.0 km
4 Inland, coastal, marine or underground waters No Not Applicable
5 State, National boundaries No Not Applicable
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No Not Applicable
7 Defence installations No Not Applicable
8 Densely populated or built-up area Yes INDORE
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Hospitals, Schools, Places of worship and Community Facilities are present near the site.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No Not Applicable
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No The project falls under seismic Zone II This Zone has been recognized as Low – Hazard Zone. Suitable seismic coefficients in horizontal and vertical directions will be adopted while designing the structures.
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No No Environmental Damage Reported from the area so far. All parameters of Air, Water, and Noise etc. will be maintained within permissible limits with proper mitigation measures.
Document to be attached
1. Upload a copy of PFR Uploaded a copy of PFR.
2. Upload a copy of EMP Uploaded a copy of EMP.
3. Upload Scanned copy of covering letter. Uploaded Scanned copy of covering letter..
4. Upload Additional attached if any(Single PDF) Uploaded Additional attached if any(Single PDF).
5. Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? Yes
6. Upload EIA Report Uploaded EIA Report.
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)18/05/2020Kindly replace the covering letter.
(2.)19/06/2020The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAnurag Maheshwari
DesignationDirector
Name of Company (Applicant Name should not be given here)M/S SHRI SHRISTI CONSTRUCTIN PVT. LTD.
AddressKhasra No 374,375/1, 375/2 part, 376/1 part, 376/2, 377/1, 377/2 part, 378/2, 378/3, 378/4, 379/1, 379/2, 379/3, 379/4, 379/5, 379/6, 379/7, 380/1/2/5, 385/P, 375/P, 385/2, 386/1, 389/1, 389/2, 390/1, 390/2, 386/2, 389/1, 390/2 AT village Bijalpur Te
Print